Project location, type of work, date work began or will begin, scheduled reopening:
First, Oregon Trail to West Fairfield, northbound lane, utility work, April 27, April 30.
Ninth, M to L, east curb lane, building construction, April 26, April 26.
Ninth, O to N, east curb lane, building construction, Dec. 2019, April 29.
10th, N to O, east curb lane, paving project, Dec. 2020, June 1.
18th, L to M, southbound lane, paving project, April 22, May 7.
35th, Sewell to 37th, sanitary sewer repair, April 21, April 28.
40th, Saltillo to Yankee Hill, roundabout project, Feb. 22, May 31.
48th, Woodland to Pioneers, northbound and southbound lanes, curb ramp project, March 31, July 27.
Northwest 56th, West Holdrege to West Partridge, paving project, March 15, July 2.
70th, Edenton to Old Cheney, southbound lane, paving project, April 19, May 5.
84th, A to Brent, southbound lane, utility work, March 29, May 7.
84th, Amber Hill to Dunrovin, paving project, April 19, May 21.
84th, South to Janssen, northbound lane, utility work, April 26, April 30.
West A, Southwest 10th to Coddington, westbound lanes, paving project, May 2020, Aug. 1.
West A, Southwest 24th to Coddington, roundabout construction, Feb. 17, Aug. 1.
A, 48th to 52nd, westbound lane, paving project, April 15, May 14.
A, Smokey Hill to 96th, paving project, March 30, July 1.
Adams, Sixth to Seventh, eastbound and westbound lanes, bridge maintenance, April 5, May 7.
Coddington, West A to West Garfield, northbound and southbound lanes, paving project, June 2020, Aug. 1.
Cornhusker, 37th to Brown, westbound and eastbound lanes, storm sewer work, March 8, April 30.
Huntington, 35th to 43rd, westbound lane, utility work, April 21, July 19.
West Holdrege, Northwest 48th to Pawnee Lake, paving project, March 15, July 2.
L, 17th to 18th, eastbound lanes, sidewalk project, April 22, May 7.
Leighton, Cotner to 70th, paving project, April 22, April 30.
O, Ninth to 11th, westbound lane, hydrant repair, April 27, April 27.
Normal, A to 35th, eastbound lane, utility work, April 5, April 30.
Q, 11th to 12th, westbound lanes, building construction, June 2020, July 1.
Rokeby, 31st to 40th, roundabout construction, Feb. 22, May 31.
Rokeby, Friedman to 84th, paving project, May 3, Oct. 15.
Saltillo, 14th to 25th, South Beltway project, April 23, May 31.
St. Paul, 48th to 49th, utility work, April 19, April 28.
Sumner, 20th to 27th, utility work, March 22, Oct. 31.
Van Dorn, 24th to 25th, westbound lane, sanitary sewer project, April 26, April 26.
To find all street closings, go to lincoln.ne.gov and type “street closures” into the search.